Case Study: Godavari Bridge

Project

Godavari Bridge

Client

South Central Railways

Year

2003

Location

Vijayawada, Andhra Pradesh, India

Task

  • The 27th span of the third Godavari Bridge had ‘settled’ into the ground by approximately 160-200mm

  • In conjunction with Fosroc India, the railway authorities determined the best repair method was to undertake jacking and grouting

  • The entire operation had to be completed within a very limited time frame (approximately 4-5 hours) as the trains could not be stopped from passing over the bridge

  • The minimum strength requirement was 15 MPa in 1hr and  30 MPa in 3hrs

Constructive Solution

  • Fosroc’s recommendation included;

  • Fosroc Conbextra HES (High Early Strength) cementitious grout mixed with 12mm aggregate to reduce initial heat build-up and thermal cracking. This combination met the arduous performance requirements while being significantly cheaper than epoxy based grouts and avoiding significant exothermic problems with this product type

  • The bridge deck was raised using jacks to allow the installation of additional reinforcement and shuttering

  • Fosroc Conbextra HES, mixed with 50% 12mm down aggregates, was used to rebuild the thickness

  • Ice cold water was used to ensure sufficient working time as ambient temperature was between 45 - 48°C

Value to Client

  • Fosroc India provided a permanent and economical solution to a long-standing problem with no hindrance to rail traffic

  • The time and cost saving to the client was an added economical benefit introduced through the use of cementitious grout in place of higher cost polymer repair products